Blade Campaign — Targets Board

Macintyre Wind Farm · Monthly Objectives · October 2026 · P6 22-Oct · Coord. 28/10
Next week
Done
Later in October
Future
Month
OCTOBER 2026
--:--

Turbines

Back to Operation
Month target OCT
3/9WTG
188 · 187 · 49 done · next 220 · then 52 · 216 TO GO
Back to op. · P6 22-Oct (commissioning) + Coord. 28/10 · 38/120 in service · 114 WTG avail. (23/10) · limit 122 / 670 MW
WTG 188 MC1 · CAT 5 · back in run03 Oct
WTG 187 MC1 · new set · commissioned 15/1015 Oct
WTG 49 Ropes R5 · repaired 03/10 · back in serviceW43
WTG 52 MC1 · lift 27–29 Oct · 181 · 182 · 18705 Nov
WTG 21 MC2 · 1/3 lifted · 466 · 467 to lift07 Nov
WTG 105 Ropes R4 · Aurora · 66% · weather09 Nov
WTG 59 Ropes R7 · GCV · 66% · weather09 Nov
WTG 94 Ropes R2 · Altus · 50%12 Nov
WTG 229 BAP P3 · Buss · 32%14 Nov
WTG 54 MC1 · reloc. 02–05 Nov16 Nov
WTG 173 MC2 · reloc. 31 Oct–04 Nov19 Nov
WTG 4 BAP P1 · Buss · 13%19 Nov
WTG 50 MC3 · broken blade · hub flipped 20/10 · not in KPI25 Nov
WTG 172 Up-tower ext. · repair done 10/10 · RR · not in KPIRR

Crane — Blade Change

MC1 · MC2 · MC3 · removal & lifting
Month target OCT
2/8WTG lifts
220 · 187 done · next 21 (1/3) · 526 TO GO
Removal & lifting finish · P6 22-Oct · IW Oct 65.6% (to 23/10) · Sep 42.5% · W43: MC1 100% · MC2 100% · MC3 94%
WTG 220 MC2 · CAT 5 · 2 blades lifted01 Oct
WTG 187 MC1 · 3 blades lifted · new set08 Oct
WTG 173 MC2 · reloc. 31 Oct–04 Nov07 Nov
WTG 54 MC1 · reloc. 02–05 Nov07 Nov
WTG 50 MC3 · blade & tower · hub flipped 20/1016 Nov
WTG 274 MC1 · reloc. 12–16 Nov19 Nov
WTG 101 MC2 · reloc. 12–16 Nov21 Nov
WTG 238 MC3 · generator repl. 23–28 Nov30 Nov

Ropes — Up Tower

7 rope crews · 4 platforms
Month target OCT
1/5repairs
49 done · 0 more fcst in Oct · crews → Nov4 TO GO
Coordination 28/10 · repair ETC · W43 weather stand-by · hold: 61 (MSW) · landowner: 41 · 206 · 233 · 262 · planned: 239 (P4) · 267
R5 · WTG 49 Aurora · back in service03 Oct · 100%
R7 · WTG 59 GCV · ropes · lamination05 Nov · 66%
R4 · WTG 105 Aurora · ropes · core install05 Nov · 66%
P3 · WTG 229 Buss · BAP · hard back prep.06 Nov · 32%
R2 · WTG 94 Altus · ropes · PS internal08 Nov · 50%
P1 · WTG 4 Buss · BAP · removing repair16 Nov · 13%
R6 · WTG 118 TBC · ropes · stand-by weather28 Nov · 32%
WTG 109 Altus · ropes · reopened · weather30 Nov · 2%

Blade Hospital

Ground repairs · B3 · Karara
34on ground
Under repair6
Repaired · to lift17
On hold4
Pending to enter7
42 repaired to date (23/10) · Oct: 210 · 516 · 683 · 646 · 6 RR ✔ ready to lift · 11 awaiting RR · 7 pending (lifter) · stock 4 new + 3 rep. sets
187✔→ WTG 52 · MC1
181 · 182✔→ WTG 52
466 · 467✔→ WTG 21 · MC2
207✔→ WTG 42 · MC2
683RR20 Oct · late
516RR→ MC2 · dest. TBC
234 · 286 · 667RRCW44
189 · 190 · 649RRCW44
210 · 633 · 646RRCW44
233hold · hardener test
672hold · rework req.
171hold · dest. TBC
685hold · PET core TÜV
Under repair · Coordination 28/10 · repair ETC · progress (Δ vs 23/10)
359 B3 · Swire · core install · +5%07 Nov · 65%
205 WTG 21 · B3 · GDES · PS int. · +5%10 Nov · 45%

Blade Movements & Logistics Departures & Arrivals board 28/10

Arrivals
T3 811 0274 0091WTG 52 → Batch 3TBC
T3 811 0275 0091WTG 52 → Batch 3TBC
T3 811 0680 0227WTG 39 → Batch 3TBC
T3 811 0429 0142WTG 47 → Batch 3TBC
Departures
T3 811 0187 0061Karrara → WTG 52 (MC1)TBC
T3 811 0516 0173Karrara → TBC (MC2)TBC
T3 811 0207 0069Karrara → WTG 42 (MC2)TBC

Safety Inspections

Macintyre Wind Farm · Inspection program · 2 inspections per person / month · DD 28/10
Acciona Energía
Nordex
2/2 done
1/2
Pending
Month
OCTOBER 2026
--:--
One Team · 44 people
OCTto 28/10
Site inspections55/ 88
Energía16/ 26
Nordex39/ 62
People done4/ 13
People done7/ 31
Abdoul NoumanBlade QualityOCT0/2
Alvaro PrietoQuality CoordinatorOCT0/2
Andrew BiagentUptower SupervisorOCT2/2
Anthony DunneBlade Repair SuperintendentOCT0/2
Ben PhilipsProject Quality ManagerOCT0/2
Benjamin OrtizAE Project DirectorOCT0/2
Braden KeeleyMain Cranes SuperintendentOCT1/2
Brett ShoeckProject Senior HS CoordinatorOCT4/2
Chelsea YoungNordexOCT3/2
Clint BartleyHSE ManagerOCT1/2
Dan MelloryLogistics SupervisorOCT0/2
Daniel RinkBlade Repair SupervisorOCT0/2
Danny HallSenior HSE ManagerOCT0/2
David PlazaCrane & Logistic ManagerOCT3/2
David WaughSuperintendentOCT0/2
Deklan BottingBlade Repair SuperintendentOCT0/2
Enzo GuliziaProject Quality ManagerOCT0/2
Grant NormanConstruction ManagerOCT0/2
Haymon RazaBlade QualityOCT1/2
Jacinto HidalgoSite Quality ManagerOCT1/2
Jahanzeb RahmanGeneral Manager - ConstructionOCT0/2
Jeff BundesenElectrical SupervisorOCT0/2
Jiuta RoundsMaterial CoordinatorOCT0/2
Keeley FaggOHS Admin ApprenticeOCT2/2
Logan DixonInstallation QualityOCT0/2
Luis SollaAE Performance ManagerOCT2/2
Mario AgeitosInstallation EngineerOCT0/2
Matt GoldingInstallation EngineerOCT0/2
Matt TranstonUptower SupervisorOCT0/2
Matthew AlipourPlannerOCT0/2
Nathan CollinsNordexOCT1/2
Oliver MaoedNordex Project ManagerOCT0/2
Pablo FernandezDeputy Construction ManagerOCT0/2
Piotr KaniaBlades Repairs ManagerOCT0/2
Rod PinoLogistics SuperintendentOCT0/2
Ruchira WellmillageQuality CoordinatorOCT0/2
Shaine MuttonHSE ManagerOCT6/2
Shane GrinterProject Senior HS CoordinatorOCT15/2
Shane MacKenzieProject Senior HSE CoordinatorOCT8/2
Shane MinahanBOP Construction ManagerOCT0/2
Steven BitcliffeBlade QualityOCT0/2
Tayfun BalikNordexOCT1/2
Zac GuntherProject EngineerOCT2/2
Zoe ScottInstallation QualityOCT2/2

Forecast

Macintyre Wind Farm · Cement Mills · 5-day hub-height wind outlook · ECMWF/BoM via Open-Meteo
Lift OK
Marginal
Wind
Rain
Lightning
Night
Crane limit
-- m/s
No-go rules
RAIN · LIGHTNING
Daylight
--:-- – --:--
--:--